With an original Programme period of 36 weeks TGM had been asked to review and suggest feasibility of reducing this duration through our experience and expertise.
Upon review TGM put forward a robust programme and completed our works over a 20 week period. Logistically the project was challenging with a live school adjacent to the site meaning timed deliveries as well as reduced 1 ton Plasterboard packs being required due to lifting restraints.